Projects
To Bid on Projects please visit City of Ogden Purchasing Homepage link for active bid openings.
Purchasing Homepage
FUNDED PROJECTS
- Maintenance Complex & West Side of Airport Improvements.
- Under Design - June 2021 - January 2022
- Out for Bids - February 2022
- Construction Start - May 2022
- Grading / Cleanup - Completed November 2022
- Utilities Upgrade (Gas, Sewage, Power, Water and Telecommunications) On-going during 2023
- Creation of West Side Entrance Road - Completed November 2022
- Schedule for Completion - December 2023
- New 120 foot Air Traffic Control Tower to replace the 64 foot Tower (FAA 100% Funded and Project Managed)
- Timeline - November 2022 - TBD 2025
- Location Siting - November 2022
- Design of 120 foot Tower - 2024
- Construction - 2025
- Completion - 2026
- $6.2 Million Expansion of Airport Terminal
- Timeline - September 2021 - October 2024
- Design - September 2021 - March 2023
- 2021-10 Ogden Airport Terminal Expansion_2022-08-11 (23 mb)
- 2021-10 Ogden Airport Terminal Expansion_2022-12-27_Progress Set (53 mb)
- 2021-10 Ogden Airport Terminal Expansion_REVIEW SET_2023-02-01 (82 mb)
- DWG phase II - Ogden City Terminal Expansion 2022-11-15 (67 mb)
- SPEC phase II - Ogden City Terminal Expansion 2022-11-15 (12 mb)
- Out for RFQ for Construction Manager General Contractor - April 2022
- Construction - June 2022 - October 2024
- RESTAURANT WILL REMAIN OPEN FOR ALL CONSTRUCTION PHASES
- Phase 1
- Widen the Terminal Access Road for both entering and exiting vehicle traffic.
- Remove the existing round-a-bout and replacement it with multiple one-way lanes for loading and unloading with a crosswalk and dividing island
- New underground conduit will be installed to allow future electrical services in the public pay parking lot, such as lighting.
- Construct a new baggage claim room on the east facing front of the terminal building
- Inside the new baggage claim room, there will be room for three car rental companies, a baggage office, an information counter, and a family restroom.
- The two existing ADA restrooms will be removed to allow for a new fire-code required exit path out of the building
- Two new ADA restrooms will be constructed where the previous Hertz Car Rental Counter was located.
- The old OGD Airport Administrative Offices will be demolished and replaced with multiple airline check-in ticket counters and the roller tables for moving the airline passenger checked baggage to TSA screening.
- The lobby area underlying tile has tested positive for asbestos and all will be removed and properly dealt with.
- All lead based paint will be removed and properly dealt with.
- The new TSA passenger screening checkpoint will be constructed.
- The terminal building basement will be demolished and a large open meeting room will be constructed.
- Two basement restrooms will be restored and remodeled.
- The beginning structural work for a three landing elevator will be constructed. The elevator itself will be installed in Phase Two.
- Schedule for Completion - Phase 1 October 2024
Other Misc. Projects
- Replacement of Windsocks and Lighting - COMPLETED JUNE 2023
- Upgrade of Segmented Circle - COMPLETED JUNE 2023
- Utah 99's Painting of 80 foot diameter Compass Rose - COMPLETED JUNE 10, 2023
COMPLETED PROJECTS
2022
- Replacement of Antiquated Airport Generator with Larger Capacity Generator
- Schedule for Completion - April 2022
- COMPLETED APRIL 2022
- Replacement of Hangar 755 Roof
- Out for Bids - March 2022
- Construction - June 2022
- Schedule for Completion - September 2022
- COMPLETED SEPTEMBER 2022
- Repair Pilot Control Lighting System Multiple Level Light Intensity
- Installation - November 2021
- Schedule for Completion - Mid-December 2021
- COMPLETED MARCH 2022
- Demolition of Hangar N-850
- Out for Bids - October 2021
- Demolition - Mid-January 2022
- Scheduled for Completion - March 2022
- COMPLETED MARCH 2022
- Remodel of Restaurant in Terminal
- Design - Completed August 2021
- Out for Bids - September 2021
- Construction - October 2021
- Schedule for Completion - March 2021
- COMPLETED APRIL 2022
2021
- Demolition of Old Tower on Top of Terminal Building.
- COMPLETED AUGUST 2021
- Time Lapse Video of Removal of Old Air Traffic Tower - Click Here
- Demolition of Hangars N-420, S-543, S-553, & N-850.
- COMPLETED JUNE 2021
- Construction of Fiber Optic Network Loop Around OGD Airport for Internet Access / Data Transmission.
- Out for Bids - June 2021
- Construction Started - August 2021
- Scheduled for Completion - January 2022
- COMPLETED DECEMBER 2021
- Construction of New Partial Parallel Taxiway Foxtrot, West of Approach End of Runway 17.
- OGD AIRPORT NORTH TIE-DOWN APRON RECONSTRUCTION, SCHEDULE II - COMPLETED DECEMBER 2021
- Granite Construction is scheduled to begin the second half of the North Tie-Down Apron Reconstruction on Tuesday June 1st, 2021.
- Phase One - June 1st - July 19th
- The pavement will be removed airside of four hangars. Each of these hangar owners & users should make arrangements to not have aircraft access in or out of their hangars between June 1st and July 19th.
- Affected Hangars - N-1302, the northmost bay only, Hangar N-1410, Hangar N-1460, and Hangar N-1504.
- Phase Two - July 19th - August 3rd
- Twenty one (21) hangars will lose the ability to get an aircraft from their hangar to the Runway & Taxiways. Each hangar owner or user will need to make arrangements to not have aircraft access in or out of their hangars between July 19th and August 23rd.
- Affected Hangars - Hangar N848, Hangar N-824, Hangars N-946, N-942, N-936, N-930, N-924, N-918, N-1038, N-1034, N-1028, N-1022, N-1016 & N-1010, Hangar N-916, Hangar N-1004, Hangar 1108, Hangar N-1116, Hangar N-1110, Hangar N-1204, and Hangar N-1302.
- Additional time will be required to core the tie-down anchor points and to paint in the striping and the tie-down "T's".
- These dates represent the best estimates for each phase, but the actual times could vary somewhat.